Skip to the content.

Releases

Cadence

Compatibility

Release Process, Coordination, and Flow

We have a weekly internal release coordination meeting to discuss the day’s release (if applicable) and set up the following release. If you have a PR against the plugin you want included in next week’s release, it should be submitted by this call. Please join the call to discuss your PR. Items included and rejected will be discussed. Attendance is optional but recommended for anyone with items they want included in the plugin. All engineering and product team members are welcome to join and participate.

All changes to brand plugins must be made in the form of mergeable PRs against the plugin, often as module updates. PRs need to be submitted by Wednesday to be considered for inclusion in the following Wednesday’s release. All other changes are considered out-of-cycle releases and require approval by an engineering director or product VP.

After the meeting, any mergeable and approved PRs will be merged into the develop branch of the respective plugin. A release branch will then be created from develop in preparation for the following week’s scheduled release. This release branch will have an associated PR targeting main, creating builds/artifacts for testing throughout the week. The goal is to create a release PR on Wednesday for the following Wednesday’s release, giving everyone a full week to test (treating it like a private beta or release candidate) and making it clear what is included in the release.

In the event a hotfix release is needed, we’ll branch from main to address the fix.

To further assist in release planning and coordination, we’ll use milestones in GitHub to indicate the target release for each PR. These milestones will reference the date initially, and once we’ve determined the release version, we will add that to the milestone title as well.

Rolling Release

  1. PRs submitted in a mergeable state before the Wednesday call will be considered for the following release.
  2. During the Wednesday call:
    • Review PRs tagged for the upcoming milestone and validate the milestone or bump the PR to the following milestone if deemed not mergeable.
    • Merge any remaining approved PRs to the develop branch. These can also be merged earlier throughout the cycle when they are approved (PRs do not need to wait for the call to be merged once they are mergeable and approved).
  3. End of Day Wednesday:
    • Create a release branch from develop and create a release PR targeting main.
    • Share build files for testing (product managers, engineers, and QA are expected to test the release candidate).
  4. Testing:
    • Any issues found during testing will need a clear discussion to determine if the fix is minor enough to be included in the release (PRs for fixes should target the release branch). If a fix cannot be made in time, we will either delay the release or revert the error-prone commit in the release branch, with the expectation that it can be fixed prior to the next release. This will be evaluated on a case-by-case basis, considering the time remaining before release, the severity of the issue, and the expected timeline to fix the issue.
  5. Release Wednesday:
    • Merge the release PR into main and tag the release. Close the milestone as complete.
    • Merge main back to develop and start the release process over. Any items discussed in our weekly call should be ready to merge to develop and create a new release branch and PR. If there are no mergeable PRs, no release branch/PR will be created for the week, but planning for the next release will still be discussed in the call.